The first How To clip shows the basics of using steps in P6.
Activity steps provide a way to break activities down into smaller units and track the completion of those units. For example, the activity Prepare for System Integration and Testing might contain the following steps:
- Establish test cases and test procedures
- Create test data
- Update SDFs
You can add as many steps to an activity as you need: some activities will require more steps to complete than others and some activities may require no additional steps at all. If progress occurs on the step, enter a percent complete in the Step % Complete column, or mark the Completed checkbox to indicate the step is 100% complete.
You can assign additional information to steps, such as cost, start and finish dates, ...
Read more...
The fundamentals of PAYE are unchanged, for example, use of codes, employers deducting tax and ... Read more...
However, a quick Google search found a connector created and published on Developer Fusion
Simple to set up and even simpler to use with the preview pane on, social connectors give you a quick view of your contacts' page.
Want to know more?
Dividend Training - 01558 822 742 or mail us
Our Partners